Reference: GAIA-C6-SP-OPM-DK-003-2,
p 18-19
Date: 1 December 2006
• Conclusion of cycle 1 - Kick-off of cycle 2
– 12-13 Oct. 06: CU6 Workshop 2 Brussels
[status: completed].
• Definition of the requests to CU2 for simulations
– 17 Nov. 06: Delivery of the 1st version
of the Simulation Requirements Document [status: completed].
– 15 Dec. 06: Delivery of the revised version
of the Simulation Requirements Document.
• Specification of the requirements for the Gaia spectroscopic
system
– 15 Dec. 06: Delivery of the software
requirement specifications for Gaia spectroscopic data processing.
• Specification, design, implementation, delivery, integration
and test of the 7 software modules defined in Table 5.
– 10 Nov. 06: Delivery of the Software
Requirements Document (SRD). [status: 85% completed].
– 8 Dec. 06: Delivery of the Software Design Document
(SDD).
– 15 Dec. 06: Validation of the Software Requirements
Document (SRD).
– 19 Jan. 07: Delivery of the Software Test Plan
(STP).
– 30 Jan. 07: Validation of the Software Design
Document (SDD).
– 30 March 07: Delivery of the software products,
of the Performance Report Document (PRD) and of the Software User Manual (SUM).
– 11 May 07: completion of the software integration,
validation and test.
• Specify and design the software products of the TWP and WP listed
in Table 6.
– 15 Dec. 06: Delivery of the draft
Software Requirements Document (SRD).
– 15 Jan. 06: Validation of the draft software
requirements.
– 15 Jan. 06: Delivery of the draft Software Design
Document (SDD).
– 15 Feb. 07: Validation of the draft software
designs.
– 16 March 07: Delivery of the revised Software
Requirements Document (SRD).
– 13 Apr. 07: Validation of the revised software
requirements.
– 13 Apr. 07: Delivery of the revised Software
Design Document (SDD).
– 11 May 07: Validation of the revised software
designs.
Table 5: List of WPs/software
modules to be specified, designed, implemented, delivered, integrated and tested
during cycle 2
610-30000 Design, develop and
test [host framework infrastructure]
620-08000 Normalisation to the continuum
630-10000 Wavelength scale and distortion map
650-07000 Radial & rot. vel. by CC with a template/mask in data space
650-08000 Radial velocity in Fourier space
650-10000 Radial & rot. velocity by minimum distance method
650-12000 Radial & rot. vel. for multi-lines by TODCOR-like method
Table 6: List of TWPs and
WPs/software products to be specified and designed during cycle 2.
620-all Spectra extraction [except
620-08000 see Table 5]
630-all Calibration of the spectroscopic instrument [except 630-10000 see Table
5]
640-05000 Astrophysical zero point
650-06000 Coarse characterisation of sources
650-14000 Detailed first look and validation: single transit
650-15000 Science alerts
660-05000 Assess source spectroscopic stability/variability